Sunday, January 11, 2009

So much done!!!

We got news on Thursday that they discontinued the color of tile we had chosen for our bathroom, so yesterday we headed back to the model house to re-pick a tile color. When we pulled up in front of our house, we saw that the siding still was not done, which annoyed us. But when we went inside, our annoyance soon disappeared. So much was done!!! They put our showers in their correct locations. Here is Ben rinsing his hair in our master bathroom :-P
They put in the pipes and the heating ducts/vents. It was pretty against the wood haha
They had poured the garage and basement floors last week, but we weren't able to get a picture. Well, here is the garage floor:
Our stairs were in!! We were able to go upstairs and downstairs for the first time! They are covered with cardboard which is adhered with this nice blue tape:
On to the basement; both our furnace and our electric box are in. The rough plumbing for the full bath that we will eventually have down there is in, as well. Below is the furnace:
They also poured our front steps:

We bought all the light fixtures we need, and ordered our ceiling fan and accessories. The work order for this week included finishing the plumbing, the eletrical guy coming for a few days, an inspection on Thursday, and insulation beginning on Friday. We will see how much gets done. And if the siding guys come back to finish that little bit of house!!

Saturday, January 3, 2009

Mystery Solved

We had to go sign a change order today, so we went by the house- still not sided. The sales director was there, so we asked when it was expected to be done. He said "Well the window had to be fixed first", which we obviously followed up with "um....what was wrong with the window?" Turns out, when they cut the windows out while they were framing, they set the large window over the front door about a foot too high. We don't know how they figured out it was incorrect, but they had to remove the window, re-cut, put the window back in, and seal the hole.
Ben and I had never noticed. But if you go back and look at the pictures of the framing, the top of the window was very close to the roof. Looking at the picture I posted yesterday, you can see where they lowered it.
Crazy, right? Siding should be finished early this coming week.

Friday, January 2, 2009

Not much new news...

We were so excited that they started to side the house...now it has come to a hault. It's looked like this for the past week, they only have that little bit to side. The siding is now covered in snow next to the garage. We are hoping that it gets finished soon!

Other than that, they poured both the garage floor and the basement floor. The next door neighbor (who seemed very nice) was out when we went yesterday (Thursday) and she told us that she saw the cement mixer at the house on Tuesday. The garage was boarded up and both the front and back doors were nailed shut, so we couldnt get in to see it. We did, however, peak through the garage window haha.

We hope everyone had a good holiday season. Happy New Year!

Saturday, December 20, 2008

It's Ex-siding!! (Get it? Exciting!)

Today we went to pick out appliances and get a more final idea of the tile/carpet/granite colors. When we pulled around the circle, we found 3 men putting siding up!!! In the snow!! We couldn't believe they were actually working on a Saturday in the snow, but there they were. They had half the back done and this much of the side when we were there. 3 hours later we drove by again on our way home; they had finished this side and had half of the other side done. Yay!!

Even though there were workers there, we decided to go inside. After walking up a thin metal plank into our mudroom, we were in. This is the landing for the stairs going up to the office. Part of our stairs got delivered, as well, but it was the short portions that come after the landing. So I'm not including a picture of those because it's only 2 steps!
This is Ben at what will be our breakfast bar. He looks a little hungry- Want some pancakes?
The workers have the windows open while they are there. As a matter of fact, the one doing the siding on the side of the house was climbing in and out of our upstairs window. haha! So, like I said it was snowing today....so here is some accumulation in our master bedroom and closet.
Best part of all- our fireplace was sitting there!!! That's its home and there it is all covered up! It will certainly be nice to have next year on a day like this!!!
We are very happy with the progress so far! Maybe we will be moving before the tentative date we have, keep your fingers crossed!!! All of the colors have been chosen, we will make sure they go together one more time before we hand in the order for good.
Happy Holidays everyone!!!!!!!!

Tuesday, December 16, 2008

A roof over our heads

I went Christmas shopping in Enfield today, so on the way home I went by the house. I'm glad I did!! When I got there, they were finishing up the roof! The roofer was finishing up the extension on our bedroom and the fireplace. Seeing that it's supposed to be bad weather tomorrow and Friday, we're glad they got it done and I'm sure they are too. They also installed all the windows and the doors! Now the wind won't blow through when we are inside anymore :-P
Please excuse the poorer than normal quality of the pictures, all I had with me was my cell phone camera.
They also put the trim around the garage doors.
The man on the roof was looking at me like I was crazy as I was taking pictures. I was thinking that the second guy drinking coffee in his utility van should have been doing work :-P

Monday, December 15, 2008

Shingles- 12/13/08

Even with the bad weather last week, they started to put the shingles on our roof. Thank goodness Friday was a nice day, that's probably when they started. Tip to roofers out there- don't leave a ladder propped up against the house for the weekend...a gust of wind came while we were there and the ladder came crashing down. Like Ben said, not going to try to catch that heavy thing! You can see if lying on the ground in front of the garage ;-P

Into the house we went, to find that our windows and doors got delivered!! Yay for glass! All the windows have the grill in between the panes, less work to do while cleaning the inside of the windows! The front door is solid, while the backdoor is full glass with the grill in the middle as well. Hopefully this week, the windows went in. That way, the freezing wind won't blow through the house while we are there!
Oh, that's our master bath tub lying in the middle of the living room, too haha. There was also a huge sheet of ice on the living room floor :-P

We have a meter box!!
Let's see, what else had they done? They marked the floor in the kitchen, showing where the range and the fridge will be. They finished framing the fireplace (which , in my becoming-an-ice-cube state, I forgot to take a picture of ), as well as the last part of the upstairs.

What will be done at the end of this week, with a forecast of rain/wintery mix? We will see Saturday!!! Saturday we will be going to the appliance store, as well as to the model house to go over all the colors for the inside again. Wish us luck!

Wednesday, December 10, 2008

It has a roof!

Wow it's been a while since we've taken these pictures. This is what we found on Friday, 12/5! It really really looks like a house now. The framing is just about complete! This is the front (excuse the shadows, the sun was setting!):

The living room/dining room will be on the first floor here, the big window on the left of the side is over the staircase, the next window is over where my reading nook will be ;-) and the other two windows will not be accessible, they are in the open space above the living room.
Bottom floor: window on right is the garage, middle is the laundry room, I believe, and the left window is the master bathroom. Top floor: two windows on the left are the office, the next two are the second bedroom, and the small one is the bathroom.
The inside framing: this room is the second bedroom, the office to the right and the hallway/reading nook to the left. The gray blob at the bottom is Ben's head :-P
We sat down with the builder on Friday to confirm cable and phone jack placement. We now have to chose all the colors for the following: carpet, tile for kitchen/master bath, grout color (who knew there are 50+ colors of grout?!?!), tile for the front of the fireplace (with grout color of course), countertops, and linoleum for the guest bathroom. I never thought that these choices would be so difficult!!!! Luckily we have a couple weeks.
The shingles were supposed to get delievered on the 9th, but with the rainy weather this week, who knows if they have. Roofing was supposed to start tomorrow, but once again, I don't think the weather will allow for this. We shall see what happens!!